PlannedNearby

York County · York Township · #26-0114

Dallastown Area SD - Springwood Rd

York Township, PA · 17,094 sq ft non-residential, school · 15.0 acres

About this project

Preliminary final land development for a 17,094 sq ft school building expansion on about 15 acres in York Township.

Official description: School Building Expansion

County recommendation: Consistent with county plan

Engineer / designer
Site Design Concepts, Inc.
Plan type
Preliminary Final Land development Building addition
Land use
Other
Water
Public water
Sewer
Public sewer

Filing history

  • 2026-07-02 · #26-0114 · Preliminary Final Land development Building addition · 17,094 sq ft

County plan review office →

The full picture AI research · Nov 1, 2026

The Dallastown Area School District plans to add a building expansion of about 17,094 square feet at Ore Valley Elementary School on Springwood Road in York Township. The school sits on roughly 15 acres, so the addition would be a modest one on a campus that already exists.

The county record calls the filing a preliminary final land development plan. That is a detailed site plan the township reviews before it allows construction. A York Township Planning Commission agenda dated August 18, 2026 lists the Ore Valley Elementary School Expansion at 2620 Springwood Road as an item to be reviewed. The search did not turn up the outcome of that review. It also found no news coverage, opposition or project page from the district or its engineer.

What it could mean nearby

Where it stands

The York Township Planning Commission had the plan on its August 18, 2026 agenda, and the county logged a filing on July 2, 2026. After the commission's review, the township supervisors usually vote on the plan. Once approved, the district can go on to building permits.

Want to weigh in? The York Township Planning Commission and then the township supervisors review land development plans at public meetings, and residents can comment there or contact the township office.

Who's behind it

Dallastown Area School District · The public school district serving Dallastown and the surrounding York County area. The county filing lists Site Design Concepts, Inc. as the firm on the plan.

Around the web

Planning terms explained
Preliminary final land development plan
A detailed site plan submitted for township review that, if approved, allows construction to move forward.
Planning commission
A township advisory board that reviews development plans and makes recommendations to the elected supervisors.
Land development
Construction or expansion of buildings and site improvements that requires formal township plan review.

Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

Scope estimate for contractors

Estimated construction value: $6.0M