PlannedNearby

York County · Hopewell Township · #25-0166

Gateway Logistics Center

Hopewell Township, PA · 301,500 sq ft non-residential, industrial · 31.0 acres

About this project

Preliminary/final land development for an industrial building of about 301,500 sq ft on roughly 31 acres in Hopewell Township.

County recommendation: Consistent with county plan

Engineer / designer
KCI Technologies
Plan type
Preliminary Final Land development
Land use
Industrial
Water
Public water
Sewer
On-lot septic

Filing history

  • 2025-09-02 · #25-0166 · Preliminary Final Land development · 301,500 sq ft

County plan review office →

The full picture AI research · Nov 1, 2026

The county filing describes a plan to build one industrial building of about 301,500 square feet on roughly 31 acres in Hopewell Township, York County. That is about the footprint of five or six football fields. The filing is for a combined preliminary and final land development plan. In that process a municipality reviews the site layout, stormwater, roads and utilities in one step instead of two.

The filing lists KCI Technologies, an engineering firm, as the firm on the plan. The records do not name the developer or a future tenant. They also do not say what is on the site now, though the size suggests undeveloped or farmed land.

No news coverage, township agendas, developer pages or opposition were found for this project. The details here come from the county record alone.

What it could mean nearby

Where it stands

The latest county filing, dated 2025-09-02, is a preliminary/final land development plan, so it is under municipal and county review. Next steps usually include township planning commission and supervisors' review, comments on stormwater and traffic, and a vote to approve, conditionally approve or deny the plan.

Want to weigh in? The Hopewell Township supervisors usually decide land development plans, after the township planning commission reviews them. Residents can comment at those public meetings, and the township office can confirm dates.

Planning terms explained
Land development plan
A detailed site plan showing the building, parking, roads, stormwater and utilities, which the municipality must approve before construction.
Preliminary/final plan
A combined review in which the township approves the design and the final plan in one step instead of two.
Stormwater management
Features such as basins that control rain runoff so it does not flood or pollute neighboring land.
Industrial use
Land used for manufacturing, warehousing or distribution rather than housing or retail.

We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

Scope estimate for contractors

Estimated construction value: $39.2M