PlannedNearby

Cape May County · Middle Township · #20250930

Institutional building, 110 Justice Way

110 Justice Way, Middle Township, NJ · 37,381 sq ft non-residential, institutional

About this project

A new institutional building of about 37,381 sq ft at 110 Justice Way in Middle Township, Cape May County, with space for lecture halls, art galleries and church use. The reported construction cost is about $15.5 million.

Official description: Lecture halls, Art Galleries, Churches, etc.; reported construction cost $15,546,787

Plan type
Building permit (new construction)
Land use
Lecture halls, Art Galleries, Churches, etc.
Status
Permit

Filing history

  • 2025-09-03 · #20250930 · Building permit (new construction) · 37,381 sq ft

NJ construction permit data (DCA) →

The full picture AI research · Nov 1, 2026

A new institutional building of about 37,381 square feet is proposed at 110 Justice Way in Middle Township, Cape May County. County records say it would include lecture halls, art galleries and space for church use. The reported construction cost is about $15.5 million.

The county filing was dated September 3, 2025. The records don't say what is on the site now, who would use the building, or which organization is behind it.

No news coverage, township agendas or minutes, hearing notices, developer pages or opposition were found for this project. This explanation relies on the county facts alone.

What it could mean nearby

Where it stands

A county planning filing was made on 2025-09-03. No township approval, hearing or decision was found online. Next steps usually include a township land-use review, and then building permits if it is approved.

Want to weigh in? The Middle Township land-use or planning board usually reviews projects like this. Residents can comment at its public meetings, but no hearing date was found.

Planning terms explained
Institutional use
A category of land use for buildings that serve the public or a community, such as schools, houses of worship and cultural centers.
Non-residential square footage
The total floor area of the building that is not used as housing.
Land-use board
A local board of residents that reviews development applications and decides whether they meet local zoning and planning rules.

We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

Scope estimate for contractors

Estimated construction value: $13.1M