PlannedNearby

Bucks County · Bristol Township · #13122

Mini-warehouse expansion at Durham Rd and Route 413

2631 and 2701 Durham Road, at the western corner of Durham Road and Veterans Highway (SR 413), Bristol Township, PA · 19,000 sq ft non-residential, warehouse & storage · 25.6 acres

About this project

An 18,000 sq ft mini-warehouse building, a 1,000 sq ft mini-warehouse building and a 764 sq ft canopy would expand an existing mini-warehouse facility on a 25.6-acre commercial site. The township Zoning Hearing Board has already approved a 53-ft building height and a larger building size.

County recommendation: Supports, with comments

Issues raised: Zoning variances for 53-ft height and 18,000 sq ft building size, Storage areas unscreened and no fencing, Waivers lack hardship reasons, Town Center design guidelines strongly encouraged, Fire lanes not shown on plan

Applicant
Amerco Real Estate Company
Engineer / designer
Colliers Engineering & Design, Inc.
Plan type
Preliminary land development
Land use
warehouse
Zoning
C Commercial, with TC Town Center overlay

Filing history

  • 2025-08-22 · #13122 · Preliminary land development · 19,000 sq ft

County review packet (meeting materials) →

Map pin is approximate.

The full picture AI research · Nov 1, 2026

The developer, which is U-Haul's real estate arm, wants to expand its existing storage center on a roughly 25.6-acre site. The site is the former Bristol Plaza shopping center at Durham Road and Veterans Highway (Route 413). The county filing lists an 18,000 sq ft mini-warehouse building, a 1,000 sq ft building and a small canopy.

The site today holds the U-Haul storage center, a U-Haul graphics printing operation, and a few remaining tenants. Most other stores have closed. News coverage says the new warehouse would go in an existing parking lot and would mainly store portable U-Box containers. The 1,000 sq ft building already exists and would be moved.

News coverage from February 2026 says the township council approved a scaled-back plan. The canopy and a planned 5,000 sq ft second-phase building were dropped. The county filing still lists the canopy, so the final plans may differ. No organized opposition was found.

What it could mean nearby

Where it stands

The township council gave preliminary and final land development approval in February 2026, after the Zoning Hearing Board granted variances. Next steps are usually meeting approval conditions, getting building and stormwater permits, and then construction. Whether construction has started was not found.

Want to weigh in? The township council has already approved the plan. Residents can still raise concerns at Bristol Township Council meetings or with the township building and zoning offices.

Who's behind it

Amerco Real Estate Company · The real estate arm of U-Haul, which owns and develops moving and self-storage sites; it bought this former shopping center in 2016.

Around the web

Planning terms explained
Land development approval
The township's formal sign-off on a site plan covering buildings, parking, drainage and landscaping.
Variance
Permission from the Zoning Hearing Board to depart from a zoning rule, such as maximum building height.
Zoning Hearing Board
A local board that decides requests for exceptions to zoning rules.
Sketch plan
An early, informal plan shown to officials for feedback before formal applications.
Curb cut
A driveway opening where a property's entrance meets the public road.

Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

Scope estimate for contractors

Estimated construction value: $2.5M