Bucks County · Plumstead Township · #12719-B
15,000 sq ft contracting building on Kellers Church Rd
Southwestern side of Kellers Church Road, about 1,500 ft north of Easton Road (PA-611), Plumstead Township, PA · 15,000 sq ft non-residential, industrial · 4.0 acres
About this project
Build a one-story, 15,000 sq ft building for a contracting business on a 3.96-acre site that is now vacant. The plan shows 30 paved parking spaces plus 20 reserve spaces. The site would be served by public water and sewer.
County recommendation: No position
Issues raised: Multiple SALDO waivers requested, including afforestation, Local historic significance needs township coordination, No loading facilities shown on plan, Alternative energy measures recommended, Sewage planning module required
- Applicant
- Hey Dude Partners, LLC
- Engineer / designer
- Van Cleef Engineering Associates, LLC
- Plan type
- Preliminary plan of land development
- Land use
- industrial
- Zoning
- LI Light Industrial
Filing history
- 2026-06-18 · #12719-B · Preliminary plan of land development · 15,000 sq ft
County review packet (meeting materials) →
Map pin is approximate.
The full picture AI research · Nov 1, 2026
A developer has filed plans to build a one-story, 15,000 sq ft building for a contracting business in Plumstead Township, Bucks County. The site is 3.96 acres on the southwestern side of Kellers Church Road, about 1,500 feet north of Easton Road (PA-611). The land is vacant today.
The plan shows 30 paved parking spaces and 20 more "reserve" spaces that would be built only if later needed. The building would connect to public water and sewer.
No news coverage, township meeting records, or developer website specific to this project was found. It is not known which contractor would occupy the building.
What it could mean nearby
- Traffic: a contractor's building usually brings daily employee trips plus work vehicles and deliveries on Kellers Church Road. The records give no traffic estimates.
- Utilities: the site would use public water and sewer, so it would not need a private well or septic system.
- Land use: a vacant 3.96-acre parcel would become a developed industrial site with parking.
Where it stands
A land development plan was filed with the county, with the latest filing dated 2026-06-18. Next the township planning commission and supervisors typically review it, and approval often comes with conditions. Construction permits follow approval.
- Jun 18, 2026 Latest county planning filing for the project
Want to weigh in? The Plumstead Township Planning Commission and Board of Supervisors would normally review the plan at public meetings, and residents can comment there. Check the township website for agendas.
Who's behind it
Hey Dude Partners, LLC
Planning terms explained
- Land development
- A formal township review of plans to build on a parcel, covering things like parking, drainage, and access.
- Reserve parking
- Extra parking spaces shown on the plan but left unpaved unless the township later requires them.
- Public water and sewer
- Connection to municipal utility systems instead of an on-site well and septic system.
- Industrial use
- A zoning category for businesses such as workshops, storage, and contractor operations.
We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
Scope estimate for contractors
Estimated construction value: $1.9M
- ~150 roofing squares (assumes 1 story)
- ~37 tons of cooling (rule of thumb 400 sq ft/ton)