About this project
Preliminary plan for 11 age-restricted leased mobile home lots on 3.4 acres off Clayton Avenue in Tilden Township, with two open space areas and a residue lot containing an existing house.
Official description: 11 Age restricted leased MobileHomes lots, 2 open space areas (0.57 acres), and residue area w/ an EX Singlefamily dwelling (0.604 acres)
- Developer
- Wilson Zimmerman
- Engineer / designer
- C2C Design Group
- Plan type
- Preliminary
- Land use
- Single-family
- Water
- Existing On Lot
- Sewer
- Existing Public
- Status
- Reviewed
The full picture AI research · Nov 1, 2026
The plan is for 11 leased lots for mobile homes on about 3.4 acres on the northeastern side of Clayton Avenue in Tilden Township. The lots are age-restricted, which means they are meant for older residents. The site is roughly 690 feet north of the Hex Highway (S.R. 4028) and W. State Street intersection.
The plan also includes two open space areas. A separate leftover lot would keep an existing house. Because the lots are leased, residents would most likely own their homes and rent the land under them. The county record does not say that.
No news coverage, developer project page, township agenda item or approval decision for this project was found online. Nothing is known about opposition, approvals or who will live there beyond the county summary.
What it could mean nearby
- Eleven new households would add some traffic to Clayton Avenue and the Hex Highway intersection. No traffic study was found.
- Two open space areas are part of the plan. The records do not say whether they would be public or private.
- Age-restricted housing usually adds few or no school-age children, though the records do not address schools.
Where it stands
The county shows a preliminary plan filed on 2025-07-29, and no later approval was found online. Preliminary plans are usually reviewed by the township planning commission and supervisors before a more detailed final plan is submitted.
- Jul 29, 2025 Latest county filing for the preliminary plan
Want to weigh in? Tilden Township's planning commission and board of supervisors normally review subdivision and land development plans at public meetings, and residents can comment there or contact the township office.
Planning terms explained
- Preliminary plan
- An early-stage subdivision or development plan that local officials review before a detailed final plan is submitted.
- Age-restricted
- Housing limited to residents above a certain age, often 55 and older.
- Residue lot
- The remaining part of a property after new lots are divided off, here holding an existing house.
- Open space
- Land set aside from building, such as a green area or stormwater area.
- Leased lot
- A plot of land rented to a resident, who typically owns the home on it.
We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
Scope estimate for contractors
Estimated construction value: $6.2M
- ~352 roofing squares
- ~11 HVAC systems
- ~11 kitchens / 22+ bathrooms
- ~30,800 sq ft of finished living space
Contractor or supplier? Get projects like this in the counties you work, by email. Join contractor early access →