Meadowood Campus - Healthcare Northeast Expansion

3205 Skippack Pike, Worcester, PA · 32,625 sq ft non-residential, institutional · 137.0 acres

About this project

Meadowood Corporation is building a three-story expansion of its existing health center on the campus at 3205 Skippack Pike in Worcester Township. The project reconfigures parking and loading areas, adds walkways, an accessible ramp, a cooling tower, and an underground stormwater detention facility, and cuts into a steep slope for a retaining wall up to about 10 feet tall.

County planning commission: Supports, with comments

Issues raised: Retaining wall cuts into 45% to 50% steep slopes, Removal of mature trees reduces canopy coverage, Net increase of 4,755 sq ft impervious surface, Loading and parking layout could be reconfigured to reduce wall size, Screening needed for adjacent residential buildings, Conflicts with steep slope goals in comprehensive plans

Applicant
Meadowood Corporation
Engineer / rep.
Woodrow & Associates, Inc.
Zoning
LPD
Approvals needed
final land development plan approval

Filing history

  • 2025-07-25 · MCPC #17-0040-008 · Land Dev Plan, Prelim Plan, Resubmission · 32,625 sq ft
  • 2025-02-07 · MCPC #17-0040-007 · Land Dev Plan, Prelim Plan · 32,670 sq ft
  • 2025-02-07 · MCPC #17-0040-007 · Land Dev Plan, Prelim Plan · 32,670 sq ft
  • 2020-01-27 · MCPC #17-0040-004 · Prelim Plan
  • 2019-10-04 · MCPC #17-0040-003 · Zoning Map Amend
  • 2017-08-01 · MCPC #17-0040-002 · Land Dev Plan, Prelim Plan · 52 homes
  • 2017-02-16 · MCPC #17-0040-001 · Land Dev Plan · 4,191 sq ft

County review letters
2025-02-07 · WORCE 17-0040-007r.pdf
2025-02-07 · WORCE 17-0040-007r.pdf
2025-07-25 · WORCE 17-0040-008r +.pdf

View all filings on the county site →

The full picture AI research · Nov 1, 2026

Meadowood Corporation, which runs the Meadowood senior living campus at 3205 Skippack Pike in Worcester Township, plans a three-story addition to its existing health center. The addition is about 32,600 square feet. The campus covers roughly 137 acres.

The work also reorganizes parking and loading areas and adds walkways, an accessible ramp, a cooling tower and an underground tank system to hold stormwater. Part of a steep slope would be cut back and held by a retaining wall up to about 10 feet tall.

Township agendas show the plan moving through review in 2025. The township supervisors were scheduled to consider preliminary approval in April 2025. The planning commission then looked at the final plan in late summer and September 2025. No news coverage or opposition was found. The township records found do not confirm a final approval.

What it could mean nearby

Where it stands

Township agendas show preliminary approval on the April 2025 supervisors' agenda. The planning commission reviewed the final plan in September 2025, and the vote was not confirmed. Final approval by the supervisors, permits and construction usually come next. The current status is unconfirmed.

Want to weigh in? The Worcester Township Board of Supervisors decides on land development plans, and residents can comment at its public meetings or by contacting the township.

Who's behind it

Meadowood Corporation · A nonprofit senior living provider that runs a retirement community in Worcester Township and has added independent living and memory care buildings to the campus in recent years.

Around the web

Planning terms explained
Land development
Township review of a plan to build or expand on a property, covering buildings, parking, drainage and access.
Preliminary approval
An early approval of the overall plan, which comes before final approval and detailed permits.
Final plan
The detailed plan the township reviews before final approval and construction.
Stormwater detention
A system that holds rain runoff temporarily and releases it slowly so nearby areas are less likely to flood.
Retaining wall
A wall built to hold back soil on a slope.

Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

Scope estimate for contractors

Estimated construction value: $11.4M