About this project
HT 1001 Washington, LLC, tied to Hightop Development, plans to demolish the former David's Bridal headquarters office building and its two-level parking garage at 1001 Washington Street in Whitemarsh Township. In their place would go 46 townhouses in eight buildings on about 3.7 acres, along with an extension of Washington Street to Lee Street. The site lies within the Schuylkill River's 100-year floodplain, and part of it is in the floodway.
County planning commission: Raises serious concerns
Issues raised: Entire site within 100-year floodplain; about 20 units in the floodway, Inconsistent with county 'Sustainable Places' vision and floodplain policy against new construction and fill, Zoning approval conditioned on FEMA Letter of Map Revision, 18 waivers requested from subdivision, stormwater and tree rules, Earlier sketch plan not supported over Riverfront overlay requirements, Inconsistent with Spring Mill Multi-Modal & Land Use Study goals
- Applicant
- HT 1001 Washington, LLC (Hightop Development)
- Engineer / rep.
- Nave Newell, Inc.
- Zoning
- HI
- Tax parcel
- 65-00-12673-00-6
- Cross street
- Lee Street
- Approvals needed
- 12 variances and 2 special exceptions granted by the Zoning Hearing Board (May 2024), conditioned on FEMA LOMR approval, 18 waivers requested (subdivision, stormwater, and tree protection)
- Utilities
- public water, public sewer
- Demolition
- Former David's Bridal office building and two-level parking garage
Filing history
- 2024-11-18 · MCPC #23-0239-002 · Land Dev Plan, Prelim Plan · 46 homes
- 2023-12-04 · MCPC #23-0239-001 · Land Dev Plan, Sketch Plan · 215 homes
County review letters
2024-11-18 · WHITE 23-0239-002r.pdf
Scope estimate for contractors
Estimated construction value: $17.0M
- ~644 roofing squares
- ~46 HVAC systems
- ~46 kitchens / 92+ bathrooms
- ~92,000 sq ft of finished living space
- ~3.7 acres of site work (grading, stormwater, landscaping)
- Washington Street extension to Lee Street
- Demolition of existing office building and parking garage
- Townhouse construction in floodplain and floodway
- Public water and sewer service connections
- Tree removal and replacement under Chapter 55